Spark Station, Mobile Power Plant

Start-up surge

Why the 20,000 W peak matters

A motor kicks hard for a split second when it starts. That split second is where generators and cheap power stations fail, and where the Mobile Power Plant doesn't.

Motors kick hard when they start

The inrush you can't see on the rating plate

A grinder, compressor or pump pulls 3 to 7 times its running power for a split second as the motor spins up. That rating plate number, 1,800 W compressor or 3,000 W welder, is the running draw. The start-up draw is much higher, and it arrives all at once.

Small generators and cheap power stations trip or stall right there. The breaker opens, the tool never starts, and you're standing in front of a dead machine holding a live one.

Spark Station handles start-up spikes up to 20,000 W, then settles to its 3,600 W rated output, so the tool starts first time. That headroom is built in, the battery management system rides through the spike instead of tripping on it.

Air compressor running1,800 W
Petrol generator peak (2.8 kW class)3,000 W
Air compressor starting6,000 W
Spark Station rated3,600 W
Spark Station peak20,000 W

Running vs start-up draw

Typical figures for common job-site tools. Every one of them starts and runs on one Mobile Power Plant.

ToolRunningStart-up surgeSurge multiple
LED work lights (x4)200 W200 W1×
Cordless tool battery chargers150 W150 W1×
4½" angle grinder900 W2,700 W3×
Hammer drill1,000 W3,000 W3×
7¼" circular saw1,400 W4,200 W3×
Submersible water pump1,000 W3,500 W4×
Air compressor (2 HP)1,800 W6,000 W3×
Inverter stick welder (140 A)3,000 W4,500 W2×

Typical figures for planning only. Check your tool's rating plate. Most hand tools run in bursts, so a real working day lasts much longer than a non-stop figure suggests.

Got a tool that won't start on other power?

Tell us the nameplate numbers and we'll confirm the start-up surge is covered, in writing.